Entry 13 Networking Project what I have done so far


Just to give an up date on the status of my project all designs are close to finished
This is as of week 6  29 of august

Site 1 

Central 

This campus is running IPV6

I  designed it to specifications given in week 1 by supervisor. 
I have setup a basic addressing scheme. I also setup dhcpv6 .
I have setup vlan 10,20,30,90. 
I have setup ether channel to have better bandwidth between devices.
also have setup password for vty,console and enable.
I have setup remote connection via ssh


Site 2

North campus & South

This campus is running IPV4

A dhcp server has been setup. addressing has been applied to interface of the router
I have Setup encapsulation dot1q for each planned vlan on the Dhcp and a dhcp pool for each vlan
Has configured  vlan 10,20, 30, 32 and 99.
have setup ether-channel on the switches where need and have also setup Hsrp where needed
also have setup password for vty ,console and enable.
I have setup remote connection via ssh
have a spanning tree portfast , bpdu guard and rapid-pvst

at this time i have tried to keep north and south up to the same stage

Research

So far I have researched on how to setup voice over ip
Have researched on how to setup IDS and IPS 
Have researched to to configure ASA 
Have done some reading up in frame relay 
also done some Research into wireless 
Also looked at different sorts of authentication
and starting to look at communication between IPV4 & IPV6


Attempted 

I have attempted to configure an ASA and IPS I still need more practice before
I imperilment it in the design
I have also attempted Configuring VOIP  on ipv4 and Ipv6  this is still in the beginning stages



Difficulties 


I have had problems with implementing a few spanning tree configuration I am still working on this .
I am going to downsize the network for testing for connectivity and if the network operates properly the simulation is being over loaded I think.
I have had problems with dhcp this maybe because the stimulation is being over loaded.


Limitation of Software

so far limitations have meant that i must use hsrp instead of what i may have use Glbp because packet tracer would not accept the commands.



This is a basic overview so far of what i have done in the project




  
  



  
  

  
  